একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়
- Get link
- X
- Other Apps
একটা বিল্ডিং এর সকল আইটেম মিলে ১০০% কিভাবে ভাগ করা হয়
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plumbing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminum work = 4%
11. EME (Lift,Generator,Substation)=10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
- STRUCTURE ~ 35%
- Footing & Column Pedestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8)
= 40%
- Roof top = 7%
TOTAL = 100% (৩৫% যেভাবে আসবে।)
সিভিল_ইঞ্জিনিয়ারিং
- BRICK WORK ~ 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (৬% যেভাবে হবে।)
- ✪ WOOD WORK ~ 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (৫% যেভাবে হবে)
- ✪ METAL WORK ~ 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill
= 15%
TOTAL = 100% (২% যেভাবে হবে।)
- ✪ PLAMBING & SANITARY WORK~ 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
- ELECTRICAL~ 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (৭% যেভাবে হবে।)
- PLASTER ~ 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (৪% যেভাবে হবে।)
- GENERAL FLOOR TILES ~ 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (৬% যেভাবে হবে।)
- TOILET & KIT WALL TILES ~ 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (৩% যেভাবে হবে।)
- ALUMINUM WORK ~ 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Common area = 5%
TOTAL = 100% (৪% যেভাবে হবে।)
- EME ~ 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (১০% যেভাবে হবে।)
- PAINT WORK ~ 3%
- Up to putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tiles = 25%
TOTAL = 100% (৩% যেভাবে হবে।)
সিভিল ইঞ্জিনিয়ারিং
- OTHERS CIVIL WORK ~ 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter
slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (৬% যেভাবে হবে।)
- UTILITY CONNECTION & BILL ~ 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA = 15%
- Utility bills = 30%
TOTAL = 100% (৩% যেভাবে হবে।)